Mechanical & Electrical work of Backwash Recovery facility at Water Treatment Plant Katugastota.
Major Equipment: 3 02 Nos. 22 kW, 270 m /hrs @ 16 m Submersible Pumps 3 02 Nos. 3.7 kW, 91 m /hrs @ 8 m Submersible Pumps 04 Nos. 400 mm Motorised Butterfly Valves 01 No. 160 A Motor Control Panel Board 01 No. Instrumentation Panel Board 03 Nos. PLC based remote control Panel Boards
|